| Job/Project | Client | Quantity | Value | Year |
|---|---|---|---|---|
| Fabrication of Project No.:R-0267A/B, R-0271A/ B&R-0272A/B (SRU-LINDE-RIL) | M/s Essar Heavy Engineering Services Ltd. Hazira | 378 MT – 6 nos. Vessels | 155 Lacs | 2013-14 |
| Fabrication, Erection of 20 mtr dia x 13 mtr high TES Tank , HVAC Project District Cooling System for GIFT City at Gandhinagar. | M/s ETA Engineering Pvt. Ltd., GIFT City, Gandhinagar | 20M dia. X 13M ht. – 1 no. TES Tank | 46 Lacs | 2013-14 |
| Fabrication, Erection of 9 mtrdiax 14 mtr high silo and allied structures for ash handling system For VPCL II, Ph I at Essar Oil Refinery Vadinar, Khambalia, Jamnagar. | M/s Essar Projects (I) Ltd. at Essar Oil Refinery , Vadinar. | 9M dia. X 14M ht. – 1 no. SILO | 45 Lacs | 2011-12 |
| Fabrication, Erection & Testing of 22 mtr diax17 mtr Sour water Cone Roof Tank | M/s Essar Projects (I) Ltd at Essar Oil Refinery , Vadinar | 22M dia. X 17M ht. – 1 no. TANK | 35 Lacs | 2011 |
| Design ,Engineering ,Fabrication & Erection /Installation ,Testing and Calibration Of 1 Water Tank | M/s Essar Oil Refinery , Vadinar | 15M dia. X 12M ht – 1 no Tank | 10.35 Lacs | 2008 |
| Design, Engineering, Fabrication & Erection/ Installation, Testing and Calibration Of 1 Water Tank for relocated Hydrogen Plant | M/s Essar Oil Refinery , Vadinar | 8M dia. X 6.5M ht – 1 no Tank | 4.3 Lacs | 2008 |
| Fabrication , erection & testing of catalyst hopper of 287MT with highest thickness of 45 mm | M/s Essar Construction Ltd. , Vadinar | 287 MT – Catalyst Hopper | 42 LACS | 2006-07 |
| Supply, Fabrication, Erection, Testing & Painting of 5.1 mtrs dia – 2nos C. S. tanks for GGS-2 & 3 for ONGC, Ankleshwar. | M/s ONGC, Ankleshwar. | 5.1M dia. - 2 nos. CS Tank | 20 LACS | 2006 |
| Fabrication, Erection & Testing of 12.0 dia x 10.0 mtrs ht. – 2 nos C.S. tanks for ONGC, Mehsana. | M/s VA TECH WABAG | 12M dia. X 10M ht – 2 CS Tank | 10.22 LACS | 2008 |
| Design, Engineering, Fabrication & Erection/ Installation, Testing and Calibration Of 1 Water Tank for relocated Hydrogen Plant | M/s Essar Oil Refinery , Vadinar | 8M dia. X 6.5M ht – 1 no Tank | 4.3 Lacs | 2006 |
| Supply, Fabrication, Erection & Testing of 3.6 mtrs dia SS 304 disc End Vessels for Pen-G Project, Masar. | M/s Torrent Gujarat Biotech Ltd, Masar, Baroda. | 3.6M dia. – SS Vessel | 5.5 LACS | 2000 |
| Fabrication, Erection, Testing & Calibration of 37 Mtrsdia tanks for AU-V project, Gujrat Refineries, Baroda. | M/s. Nicco Corp. Ltd. (Proj.Div.) | 37M dia. - Tank | 28.8 LACS | 1999-00 |
| Job/Project | Client | Quantity | Type | Value | Year |
|---|---|---|---|---|---|
| Ethane GCU Shutdown works , Dahej | M/s RELIANCE INDUSTRIES LTD., DAHEJ | 2,398 Inch dia. & 6,918 Inch mtr. & Tie-Ins – 63 nos. | CS/SS – upto 15mm - NIBR | 110 LACS | 2016 |
| Ethane Gas Cracker Modification – ISBL Area Unit Piping job, Dahej | M/s RELIANCE INDUSTRIES LTD., DAHEJ | 75,000 Inch dia. & 1,30,000 Inch mtr. | CS/SS – upto 24mm IBR/NIBR – Unit Piping | 875 LACS | 2016 |
| Elbow Replacement, Strainer removal, Pump piping modification, On line clamps Removal & Cooling water line replacement Jobs during VGO-HT Short Shutdown | Essar Oil Limited, Vadinar | Lumpsum amount | Up to 6-inch CS Pipes of Heavy Thickness | 42 Lacs | 2016 |
| A/G Piping works for Train III at PX4 area , RIL J3 Jamnagar | M/S RELIANCE INDUSTRIES LIMITED, JAMNAGAR | 15,000 Inch dia. & 51,000 inch mtr. | CS/SS upto 20mm thk – Unit Piping | 546 LACS | 2016 |
| Pneumatic Conveying System works at C2 Complex, RIL J3 Jamnagar | M/S RELIANCE INDUSTRIES LIMITED, JAMNAGAR | 10,000 Inch dia. & 68,000 inch mtr. | SS/CS upto 16mm thk – Unit Piping | 471 LACS | 2016 |
| Process Piping Schemes (PS-5009) at CDU-1 during Turnaround’15 | M/S ESSAR OIL LIMITED , VADINAR | 6,000 Inch dia. & 9,085 Inch mtr. | CS/AS-P5,P7 - upto 15mm NIBR - Process Piping | 157 LACS | 2015 |
| Rack piping work around PX4 of our SEZ refinery for J3 project, Jamnagar | M/S RELIANCE INDUSTRIES LIMITED, JAMNAGAR | 10,800 Inch dia. & 1,89,000 Inch mtr. | CS/SS – Rack/Unit- upto 15mm – IBR/NIBR | 542 LACS | 2015 |
| Above Ground piping in OSBL area of CCPP project at RIL Dahej | M/s RELIANCE INDUSTRIES LTD., DAHEJ | 45,000 Inch dia. & 1,10,000 Inch Mtr. | CS/SS/AS-P91 – upto 54mm – IBR/NIBR | 1210 LACS | 2015 |
| Above Ground Piping fabrication , erection and associated works for CCPP Dahej | M/S RELIANCE UTILITIES AND POWER PVT. LIMITED, DAHEJ | 25,000 Inch dia. & 1,15,000 Inch Mtr | CS/SS – upto 16mm –IBR/NIBR | 235 LACS | 2015 |
| Warehouse Piping job for PTA5 & 6 at DMD Expansion Project | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | 27,100 Inch dia. & 34,400 Inch Mtr | CS/SS – upto 12mm – Unit NIBR | 243 LACS | 2015 |
| Pneumatic conveying system Piping fabrication & erection for PTA6 at DMD Expansion Project | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | 16,000 Inch dia. & 25,000 Inch mtr& 80MT Equip | SS – upto 12mm | 200 LACS | 2014-15 |
| Piping Works for Cooling Water System at PTA6# area at DMD Expansion Project at RIL Dahej | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | 3,300 Inch dia. & 17,400 Inch mtr. | CS – upto 24mm – Unit NIBR | 37 LACS | 2015 |
| Fabrication & Erection of AG Piping works of STG at CPP Area for RIL Dahej Project | M/S RELIANCE UTILITIES AND POWER PVT. LIMITED, DAHEJ | 4,200 Inch dia. & 6,200 Inch mtr. | CS/SS/AS – upto 16mm – IBR/NIBR | 25 LACS | 2014 |
| Nozzle Welding & Piping for workaround in ETP Area for RIL Dahej. | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | 5,800 Inch dia. & 4,500 Inch mtr. | CS – upto 10mm – Unit NIBR | 33 LACS | 2014-15 |
| Piping Fabrication & Modification Jobs - Demax (DHDT) | M/S ESSAR OIL LIMITED , VADINAR | 46,000 Inch dia. & 96,000 Inch mtr. | CS/SS/AS – upto 40mm – IBR/NIBR | 585 LACS | 2014-15 |
| Pneumatic conveying system Piping fabrication & erection for PTA5 at DMD Expansion Project | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | 20,000 Inch dia. & 35,000 Inch mtr. & 90MT Equip. | SS – upto 10mm | 274 LACS | 2014 |
| Fabrication & Erection of SVH line (Very High Pressure Steam line) Alloy Steel- P-91 material in OSBL for RIL Dahej Project | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | 9,800 Inch dia. & 24,500 Inch mtr. | AS-P91 – upto 37mm - IBR | 416 LACS | 2014 |
| Titanium Piping Erection for PTA-6 at DMD , Dahej | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | 25,000 Inch mtr. | Titanium – upto 40mm | 31 LACS | 2014 |
| Fabrication, Erection & Testing of FW piping at GCPTCL, Dahej | M/S GUJARAT CHEMICAL PORT TERMINAL CO. LTD. | 13,000 Inch dia. & 42,000 Inch mtr. | CS – upto 10mm | 71 LACS | 2013-14 |
| A/G Piping & Equipment erection works in ASU area of DMD Exp. Project , Dahej | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | 20,000 Inch dia. & 24,000 Inch mtr. | CS/SS – 19mm NIBR | 121 LACS | 2013 |
| Fabrication, erection & testing of above ground piping and fabrication, erection of structural steel works for HMU II & associated service at EOL Refinery site, Vadinar | M/S ESSAR PROJECT INDIA LTD. , VADINAR | 90,000 Inch dia. & 1,25,000 Inch mtr. & 1200 MT Structure | CS/SS/GI/AS – upto 32mm – IBR/NIBR – Process Piping | 561 LACS | 2012-14 |
| Fabrication, erection & testing of LP Piping at 1200 MW power plant | M/S ESSAR PROJECT INDIA LTD. , VADINAR | 22,000 Inch dia. & 66,000 Inch mtr. | CS – upto 10mm NIBR | 87 LACS | 2011-12 |
| Fabrication, erection,testing & modification of process piping of 3 no HSD Tanks | M/S ESSAR PROJECT INDIA LTD. , VADINAR | 60,000 Inch dia. & 2,30,000 Inch mtr | CS – upto 16mm NIBR | 273 LACS | 2011-12 |
| Fabrication,Erection, Testing & Mechanical Completion of A/G Piping for 2X750 TPH Co-Generation Power plant (VPCL Phase-IIA) at refinery site, Vadinar | M/S ESSAR PROJECT INDIA LTD. , VADINAR | 70,000 Inch dia. & 2,00,000 Inch mtr. | CS/SS/AS-P5,9,11,22,91 – upto 50mm –IBR/NIBR | 625 LACS | 2011-12 |
| Fabrication , erection & testing of Fire water piping network | M/S ESSAR PROJECT INDIA LTD. , VADINAR | 1,15,000 Inch dia. & 3,95,000 Inch mtr. | CS – upto 11mm NIBR | 350 LACS | 2011-12 |
| Manufacturing of NACE Pipes & Fittings for flare system, Size from dia 90'' to 106'' and thickness upto 24mm | M/S ESSAR PROJECT INDIA LTD. , VADINAR | 1,00,000 Inch dia. & 2000 MT pipe spools | NACE CS – upto 30mm | 303 LACS | 2010-11 |
| Job/Project | Client | Quantity | Value | Year |
|---|---|---|---|---|
| Miscellaneous Structural works in ASU Area for RIL Dahej Project | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | Over 20MT | 4.54 LACS | 2014 |
| Structural Fabrication & Erection works for ASU area at RIL Dahej | M/S RELIANCE INDUSTRIES LIMITED, DAHEJ | Over 150MT | 23.3 LACS | 2013-14 |
| Modification of Structure after drawing revision & Balance Fabrication, erection of Strl. Steel for Pumphouse at Intake Well | M/S ESSAR PROJECTS INDIA LTD. , SALAYA | Over 200MT | 34.94 LACS | 2013 |
| Fabrication & Erection of Structure Steel work for Riser Pipe Support Structure | M/S ESSAR PROJECTS INDIA LTD. , VADINAR | Upto 80MT | 11 LACS | 2011 |
| Fabrication & Erection of Structure Steel work for RWTP | M/S ESSAR PROJECTS INDIA LTD. , VADINAR | Upto 60MT | 9 LACS | 2011 |
| Fabrication & Erection of Structure Steel work for TG Building | M/S ESSAR PROJECTS INDIA LTD. , VADINAR | Upto 150MT | 39 LACS | 2011-12 |
| Fabrication & Erection of Structure Steel work for OSBL Pipe rack | M/S ESSAR PROJECTS INDIA LTD. , VADINAR | Upto 60MT | 7.8 LACS | 2011-12 |
| Fabrication & Erection of Structure Steel work for Pipe rack | M/S ESSAR PROJECTS INDIA LTD. , VADINAR | Over 500MT | 160 LACS | 2011-12 |
| Fabrication & Erection of Structure Steel work for WWTP Pipe rack | M/S ESSAR PROJECTS INDIA LTD. , VADINAR | Upto 100MT | 15 LACS | 2011 |
| Fabrication & Erection of Structure Steel work for 2x110 MW Power Plant | M/S ESSAR PROJECTS INDIA LTD. , VADINAR | Upto 80MT | 10 LACS | 2010 |
| Fabrication & Erection of Structures for Pump house in multiple orders | M/S ESSAR PROJECTS INDIA LTD. , VADINAR | Upto 350MT | 30 LACS | 2009-10 |
| Fabrication & Erection of Structures and discharge duct liner for PS1,2,4&5 in multiple orders- 2500 MT | M/S SAURASTRA BRANCH CANAL PROJECT, LAKHTAR | Over 2500MT | 250 LACS | 2004-08 |
| Structural fabrication & erection appox . Qty 700MT - ANJAR | M/S WELSPUN / SIMPLEX CONCRETE PILES INDIA LTD.,ANJAR | Over 700MT | 28 LACS | 2004 |
| Erection of fabricated structure appox. Qty – 800MT - HAZIRA | SHELL LNG -SIMPLEX CONCRETE PILES (INDIA) LTD. | Over 800MT | 70 LACS | 2004-05 |
| Job/Project | Client | Quantity | Value | Year |
|---|---|---|---|---|
| Revamping of VDU Heaters during shutdown at EOL refinery, Vadinar | M/s EOL, Vadinar | 2000 inch dia. & 7500 inch mtr. | 200 LACS | 2015 |
| Modification & replacement of Heater coil in CDU-1 during shutdown & pre-shutdown at EOL refinery, Vadinar | M/s EOL, Vadinar | 900 Inch dia. & 3500 inch mtr. | 79 LACS | 2015 |
| Fixing of SS Liner for Trench & Pit at PTA-6 area for RIL Dahej Project | M/s RIL ,Dahej | Above 400MT | 268 LACS | 2014 |
| Fabrication of Misc. Equipment for PTA-6 for RIL Dahej Project | M/s RIL ,Dahej | 33 LACS | 2014 | |
| Manpower Support for Fabrication of spools at PFS and Multiple orders | M/s RIL , Jamnagar | 2,00,000 Inch dia. | 902 LACS | 2014-2015 |
| HVAC Project District Cooling Plant at Ahmedabad (4248) / Fabrication, Erection & Testing of TES Tank | M/S ETA ENGG. PVT. LTD. , GIFT CITY, Ahmedabad | 52 LACS | 2014 | |
| Civil works for PTA-5 Plant at Dahej (PIT & LINER) | M/S RIL – L&T Hydrocarbons | 162 LACS | 2013 | |
| Fabrication of Vessels | M/S EHES , HAZIRA | 77.6 MT – 20mm | 25.99 LACS | 2013 |
| Modification & Rectification of VBU Heater during SHUTDOWN | M/S ESSAR PROJECTS INDIA LTD. ,VADINAR | 69 LACS | 2012 | |
| Fabrication of Chimney Can Duct for 2x640 MW plant | M/S ESSAR POWER GUJARAT INDIA LTD. ,SALAYA | 35 LACS | 2011 | |
| Fabrication of Vessels | M/S EHES , HAZIRA | 54 LACS | 2011 | |
| Revamping of CDU/VDU Heaters Shutdown work involving AS, SS,CS coil change | M/S ESSAR PROJECTS INDIA LTD. ,VADINAR | 1500 Inch dia. Dism. & Revamp. | 314 LACS | 2011 |
| Fabrication & Erection work for DHDT Heater with AS,SS coil piping | M/S ESSAR PROJECTS INDIA LTD. ,VADINAR | 900 Inch dia. Coil replacement | 214 LACS | 2010-11 |
| Fabrication of 6.8 mtrs dia. Flue Can Duct for Salaya Power plant 2x640MW | M/S ESSAR POWER GUJARAT INDIA LTD. ,SALAYA | 6.8m dia. Flue Can Duct | 140 LACS | 2009-10 |
| Fabrication of 4.7 mtrsdia, Flue Can Duct | M/S EPIL , VPCL | 4.7m dia. Flue Can Duct | 54 LACS | 2010 |
| Fabrication & Erection of 2 nos 5.4 dia x 65 mtrs high stack | M/S EPIL , VPCL-II | 60 LACS | 2008-09 |
Any Routined ANNUAL TURNAROUND of Plant, Rendering our services in warfooting in the event of unforeseen sudden extreme EMERGENCY CRISIS on peck of call, refurbishing the damaged equipment in Situ, braving all adversities, inclusive dismantling, item replacing with newly manufactured/fabricated ones.
| Job/Project | Client | Quantity | Value | Year |
|---|---|---|---|---|
| VDU Revamping during Turnaround 15, EOL Refinery, Vadinar | Essar Oil Limited | 4500 Inch. Dia./9000 Inch. Mtr./ 700 MT | 200 LACS | 2015 |
| Modification & Replacement of Heater Coil in CDU-1 during shutdown at EOL Refinery, Vadinar | Essar Projects India Limited | 900 inch dia./3500 inch mtr. | 79 LACS | 2015 |
| Process Piping Schemes (PS-5006) at CDU-1 during Shutdown at EOL Refinery, Vadinar | Essar Oil Limited | 6000 inch dia../9085 inch mtr. | 157 LACS | 2015 |
| Installation of Isolation Valve at DHDT plant during Shutdown at EOL Refinery, Vadinar | Essar Oil Limited | 600 inch dia./1000 inch mtr. | 22 LACS | 2015 |
| APH Bottom Hopper Repair jobs at CDU-1 during Shutdown at EOL Refinery, Vadinar | Essar Oil Limited | 64 MT | 25 LACS | 2015 |
| Urgent replacement of DHDT vessel dish end during Shutdown at EOL Refinery, Vadinar | Essar Oil Limited | 4 MT | 6 LACS | 2015 |
| Dismantling of Old APH & erection of New APH at HMU-I during Shutdown , EOL Refinery, Vadinar | Essar Project India Limited | 3000 inch dia./1000 inch mtr./55 MT | 24 LACS | 2014 |
| Fabrication, erection, testing & mechanical completion of APH piping work during shutdown at HMU-I , Vadinar | Essar Project India Limited | 200 inch dia./ 800 inch mtr. | 7.5 LACS | 2013 |
| Modification & Rectification of VBU Heater during Shutdown, EOL Refinery, Vadinar | Essar Project India Limited | 800 inch dia./1000 inch mtr. | 77 LACS | 2012 |
| Revamping of CDU/VDU Heaters shutdown work involving AS,SS,CS Coils at EOL Refinery, Vadinar | Essar Project India Limited | Coil replacement | 314 LACS | 2011 |
| Fabrication of SS 316/CS piping during Shutdown, Masar | Torrent Gujarat Biotech Ltd. | 9.5 LACS | 2001 |