Over 4000 MT of Structural Steel Erected within a schedule period along with a single lift module erection of 49 MT of 4 Numbers.
Very pleasure to announce that successful completion of hydro test of 1,04,544 INM (88.6%) of base scope IIR Phase - I.
Fabrication, Erection of Piping over 14,000 Inch Dia. and 49,000 Inch Mtr. along with structural erection of 750 MT.
Successfully completed fabrication and erection work of 1,29,500 Inch Dia, 1,15,700 Inch Mtr, 147 MT of Structure & 189 MT of SS Tanks fabrication in a compact schedule of four and half months.
Victoriously executed 1110 MT of multiple equipment Erection with 3 numbers of cranes specially with a tyre mounted crane of 450 MT.